Strength and expertise on the track
Perfect organization at Linate Cantiere 24 hours a day, 7 days a week: a unique operation of great scope. Started on July 27 in Linate the construction site for the renovation of the runway of the Milan airport, was completed in perfect timing for the first flight of October 26.
The exceptional nature of the project is represented by the tight schedule, a prerogative of the work involving the airports: it began on 27 July with the closure of the runway and reopening scheduled for 26 October. During these 90 days, teams of professionals have alternated to better deal with the operations, 24 hours a day, seven days a week.
Area of Paving
150.000 sqm
Laid asphalt
125.000 ton
Electrical wiring
93 km