A record-breaking dismantling
The demolition also involved all the so-called “connective” structures (escalators, elevators and the reinforcement of the floor, etc.). The pedestrian link consisted mainly of metal structure, with a length of about 75 meters and a plan width of about 8 meters and a total weight estimated at about 400 tons. The entire pedestrian walkway was removed, in just two nights, by the use of a 750-ton crane truck on which cut sections of the walkway were loaded and disassembled. Subsequently, the removed footbridge segments were removed from the construction site area using modular trolleys.